Report on the findings of the NSW Environment Protection Authority’s review of Snowy Hydro Limited Cloud Seeding Program: 2024 Annual Compliance Report (2025)

Government Record · NSW Environment Protection Authority · December 3, 2025

NSW Environment Protection Authority, 2025-12-03: Regulator's compliance review of the last reporting year of the Snowy program. It finds Snowy Hydro complied with the Act and the Environmental Management Plan, records that no seeding occurred in 2024 (the program was paused for review), and reports that monitoring data showed no evidence of significant adverse environmental impacts, including no detectable effect on precipitation downwind of the target area in records from 1990-2024 and no broadscale increase in environmental silver. It also records criticisms from DCCEEW's Environmental Protection Science section over unexplained elevated silver in two of 36 soil samples and recommends ecological risk sampling.

No cloud seeding operations were undertaken in 2024 and therefore no cloud seeding agent was dispersed over the Target area.

NSW Environment Protection Authority, 2025-12-03: Regulator's compliance review of the last reporting year of the Snowy program. It finds Snowy Hydro complied with the Act and the Environmental Management Plan, records that no seeding occurred in 2024 (the program was paused for review), and reports that monitoring data showed no evidence of significant adverse environmental impacts, including no detectable effect on precipitation downwind of the target area in records from 1990-2024 and no broadscale increase in environmental silver. It also records criticisms from DCCEEW's Environmental Protection Science section over unexplained elevated silver in two of 36 soil samples and recommends ecological risk sampling. Not a study – regulatory compliance review (page footer 'Updated 03 December 2025'; read 2026-11-22). Issuer: NSW EPA, reviewing Snowy Hydro's self-reported 2024 Annual Compliance Report; the EPA is the oversight body, not the operator, though it is reporting on a program it regulates. Monitoring described: soil, water, sediment and precipitation sampling under the EMP, compared against background and long-run records (1990-2024 precipitation; 36 soil samples in the 2024 round). No sample size for the seeding itself because no seeding took place. No declared conflicts. Route: plain HTML fetched with curl, tag-stripped to text. Study type: regulatory record.